Shotwell Road Bridge Replacement, Construction, workers

Franklin County Public Works

Cochran performed the surveying, design, and bidding documents for this federal aid bridge replacement, the bridge no. 18600201 (F-148), on Shotwell Road in Franklin County.  The project included clearing, grubbing and stripping; excavation and embankment in place; guardrail, 2,155 sy of bituminous pavement; type 2 rock blanket; construction signage; pre-bore for piling; 226 sy of slab on concrete I-Girder; 74 ft prestressed concrete I-Girders; seeding, mulching and fertilizing; and pavement striping.  This project was federally funded and all construction documents were required to meet standards for project delivery as outlined in MoDOT’s Local Public Agency (LPA) manual.  Cochran performed the construction administration and inspection services for the County.