Green County PWSD No. 1
Cochran performed the design, bid administration, and construction administration for the improvements to Greene County PWSD No.1’s Water Storage Tank #2. The project included demolition of the existing 6-inch diameter dedicated fill line, including structural supports and insulation, construction of an 8-inch diameter dedicated fill line, construction of a 6-inch diameter mixing system, construction of a doghouse pipe enclosure, installation of a removable silt plate on the existing 12-inch diameter distribution line and exterior cleaning of the tank. The improvements were completed in June 2018.